As of the 1st of October, the tunnel is 68% complete. Tunnel men have so far dug out 105.1km of tunnels out of the 153.5 km planned. In September they drove a total of 480m of tunnel, hard going at times clearly, in the Sedrun subsection, driving east, they are advancing 1.4 meters a day.